Using reports
60 Issue 3 July 2001 Send feedback: document@avaya.com
Removing scheduled reports
As your needs change, you may want to remove certain reports
from the report scheduler. The following example removes
Job 12 from the report scheduler.
Tip:
You can use
list report-scheduler
to determine which reports
you want to remove.
To remove job 12 from the report scheduler:
1. Type
remove report-scheduler 12 and press RETURN.
The Report Scheduler screen appears.
2. Press
ENTER to remove the report.
NOTE:
If you want to print a different report, you must remove the old
report from the report scheduler, and then add the new report.